LA30 Shelter Demolition

Share
Client
Location
Completed
Aug 2024
Value
$720,000
Removal and decontamination of a legacy shelter structure to support logistics flow and environmental compliance.

KW Civil was contracted to demolish a contaminated shed structure, including safe waste sorting, decontamination, and disposal. The cleared space was needed to facilitate transport access for future modular infrastructure.

Strict air quality monitoring and PPE protocols were enforced throughout demolition. A waste management plan was developed to minimise environmental impact and ensure compliance with local disposal regulations.

All works were completed safely and ahead of schedule, with zero safety incidents. The project delivered clean clearance of the structure with minimal disruption and strong environmental controls.

Scope of Works

Land Clearing

Rehabilitation

Excavator demolishing an old building during mining operations in the Pilbara region – featured in KW Civil & Construction’s history of mining post